How big is the data center construction boom?

Data centers are carrying the growth in U.S. commercial construction. The U.S. Census Bureau’s preliminary September 2026 figures put private data center construction at a seasonally adjusted annual rate of $96.5 billion, the highest on record and up from $50.7 billion a year earlier.

MeasureFigureSource
Private data center construction spending (annual rate)$96.5 billion, up 90% in a yearU.S. Census Bureau, September 2026 (preliminary)
Share of all private nonresidential construction spendingAbout 12%Calculated from the same Census table
Actual spending, January to September 2026$54.2 billion, up 49% from the same months of 2025U.S. Census Bureau (not seasonally adjusted)
Other private nonresidential spending (excluding data centers and power)Down 7.8% in a yearAGC analysis of Census data, September 2026
Forecast for data center spendingUp 33% in 2026 and 24.7% in 2027AIA Consensus Construction Forecast, July 2026

Outside data centers, the market is flat. AIA’s forecast panel expects commercial spending without data centers to fall 1% in 2026 and rise 1% in 2027. For the wider picture, see our construction industry trends review and outlook.

This guide is part of our series on how to find construction projects before they go to bid.

Where are data centers being built?

Northern Virginia is still the largest data center market, but construction has spread. CBRE reports that Atlanta passed Northern Virginia in capacity under construction for the first time in the first half of 2026.

MarketCapacity under constructionSource
Atlanta2,882 MW, up 52% in a yearCBRE, first half of 2026
Northern Virginia2,420 MW, with vacancy at 0.2%CBRE, first half of 2026
Phoenix1.7 GWJLL, midyear 2026
Dallas-Fort WorthMore than 765 MW, about 95% preleasedCBRE, first half of 2026
Texas (statewide)26 GW existing and under construction combinedJLL, midyear 2026

Across North America, JLL counts 66 GW under construction, 95% of it already committed to tenants. It says 77% of the capacity in development is in “frontier markets” outside the traditional hubs, and big campuses are landing in Louisiana, Indiana, Michigan, Mississippi, New Mexico, and Georgia.

For where the largest projects of every type are going, see the largest construction projects in the U.S. by state and the states with the most construction.

Major data center projects to know

ProjectLocationOwnerSizeStatus (as reported)
HyperionRichland Parish, LAMeta5 GW, more than $50 billionUnder construction; expansion announced July 2026
Lebanon campusLebanon, INMeta1 GW, more than $10 billionBroke ground February 2026
Northwest Louisiana campusesCaddo and Bossier parishes, LAAmazon, with STACK Infrastructure$18 billion across 3 campusesTwo campuses started in 2026; third announced August 2026
Central Mississippi expansionMadison County and Clinton, MSAmazon Web Services$12 billion addedAnnounced April 2026
Project JupiterSanta Teresa, NMSTACK Infrastructure, for Oracle and OpenAIAbout 1,750 MW of IT capacityFoundations and structure under way; completion projected for 2028
Saline Township campusSaline Township, MIRelated Digital, for OracleMore than 1 GW; $16 billion financingConstruction began February 2026
FairwaterMount Pleasant, WIMicrosoft$3.3 billion first site; about $4 billion second siteFirst site going live; second under construction (April 2026)
Project CamelliaEffingham County, GAOpenAI3.2 GW, phased 2028 to 2032Announced July 2026
Sturgeon County campusSturgeon County, ABMeta1 GW, more than C$13 billionBroke ground July 2026
Bell AI FabricNear Regina, SKBell Canada300 MW; expansion to 1.2 GW approvedUnder construction since April 2026; first data hall expected in the first half of 2027

Status changes quickly on projects this size. Treat this list as a starting point, and confirm the stage and the current contacts before you call.

Data center construction in Canada

Canada’s pipeline is large but limited by power. Alberta has about 19,565 MW of data center load requested, against a record provincial peak of about 12,800 MW, and its first 1,200 MW allocation is fully used. Ontario has about 7,000 MW of data center requests in its grid queue.

Ontario’s proposed rules would have new data centers pay all of their energy costs, with no cash incentives.

Is data center construction slowing down?

Not overall, but parts of the pipeline are. Spending was still climbing in September 2026, yet several constraints are pushing schedules out and stalling some projects.

ConstraintWhat the numbers saySource
PowerGrid connections in primary U.S. markets take more than four years on average. Texas has about 474 GW of large loads asking to connect, about 90% of them data centers.JLL, January 2026; ERCOT, June 2026
EquipmentGenerator step-up transformers take more than 160 weeks to arrive; backup generators about 130 weeks.Wood Mackenzie via Reuters, July 2026; Linesight, April 2026
Labor85% of data center contractors with electrician openings have trouble filling them; 44% report delays from worker shortages.AGC and NCCER survey, September 2026
Approvals18% of data center contractors had a project canceled, postponed, or delayed by moratoriums or slow approvals in the past six months.AGC and NCCER survey, September 2026
MaterialsAluminum mill shapes up 27%, steel mill products up 23%, and copper and brass mill shapes up 21% in a year.AGC analysis of producer prices, August 2026

Rules are tightening too. In September 2026, the Texas governor directed the state environmental agency to halt data center permits until a grid operator audit is finished. Denver, Minneapolis, and Seattle are among the cities that adopted temporary moratoriums in 2026.

For sellers, delays cut both ways. A longer schedule gives you more time to reach the team, and equipment shortages reward suppliers who can deliver on time.

What work does a data center project need?

A data center is a building-systems project. Cost consultant Linesight puts mechanical, electrical, and plumbing work at 30% to 50% of a hyperscale project’s cost, and Cushman & Wakefield names power infrastructure as the largest single cost category, at 21%.

Cushman & Wakefield’s 2026 guide puts the all-in cost of a new U.S. or Canadian data center at about $17.6 million per MW, excluding computer chips, up 21% since late 2024. Turner & Townsend puts U.S. construction cost alone at about $12.08 per watt.

Trade or supplierTypical scope on a data center
Electrical contractorsMedium-voltage distribution, switchgear, UPS systems, busway, generators, and grounding
Mechanical and HVACChillers, cooling towers, air handlers, and piping for liquid cooling
Concrete and structuralFoundations, large slabs, precast or tilt-up walls, and structural steel
Fire protectionSprinklers, pre-action and clean-agent suppression, and detection
Low-voltage and securityFiber, structured cabling, access control, and cameras
Site and civilGrading, utilities, stormwater, roads, and substation pads

Owners increasingly buy this work as programs. Linesight describes owners moving to program-wide MEP procurement, standardized scopes, prefabricated electrical rooms and mechanical skids, and multi-building campus awards. Once a trade partner is on a program, it can stay for years.

Schedules are long and phased. Bell Canada started building near Regina in April 2026 and expects its first data hall in the first half of 2027, while Meta expects full build-out of its Louisiana campus by 2036.

How do data center projects start?

A data center leaves a public trail long before construction. These are the records worth watching, roughly in the order they appear.

  • Land and rezoning. Developers assemble large sites near power and fiber, often through companies with unfamiliar names, then seek rezoning or a special-use permit at public hearings.
  • Utility agreements. Will-serve letters, energy supply agreements, and large-load interconnection requests show that a utility is planning to serve the site.
  • Tax incentives. Abatements and sales tax exemptions are voted on in public meetings, and some states publish lists of qualifying projects.
  • Environmental permits. Air permits for backup generators, water and wastewater permits, and stormwater permits follow as the design firms up.
  • Building permits. These come last, usually after the owner has chosen its builder and most major trades.

Many agreements are covered by confidentiality terms, so the paper trail is incomplete. Our guide to construction reports and permit data covers where to find permits once they are filed.

Watching all of this by hand across a territory is slow. A verified project database does the research for you, and every project comes with a named contact, phone number, and email.

Who decides on a data center project?

Data center owners fall into three groups, and each buys construction differently.

Owner typeWho they areHow they buy
Hyperscale, self-builtLarge cloud and AI companies building their own campusesRepeat design-build or construction manager partners, preferred vendor programs, multi-year campus awards
Colocation and wholesale developersCompanies that build capacity and lease it to tenantsDeveloper-led, often built for a signed tenant, with the general contractor chosen early
Enterprise and edgeBanks, hospitals, universities, telecom companies, and governmentsSmaller projects with more conventional bid or negotiated contracts; public owners follow procurement rules
If you areContact firstWhy
General contractor or construction managerOwner’s development or construction leaderThey choose the builder, often for several buildings at once
Electrical or mechanical subcontractorThe builder’s preconstruction and MEP procurement teamThey build the trade packages and the preferred partner list
Building product manufacturerEngineers of record and the design-build teamThey write the specifications and approve equivalents
Equipment supplierOwner’s procurement group and the builderLong-lead equipment is often bought early, sometimes by the owner directly

Because design-build and construction manager contracts bring the builder in during design, our guide to design-build vs. design-bid-build is worth a read before your first call. Manufacturers should also see how to get your product specified and how others use construction project data for manufacturers.

What does 2027 look like for data centers?

Forecasters expect growth to continue at a slower pace. AIA’s July 2026 consensus forecast calls for data center spending to rise 24.7% in 2027, after 33% in 2026, with individual panelists ranging from 14% to almost 38%.

Demand is not the limit. CBRE reports primary-market vacancy at a record low of 1.4% and less than 1,500 MW left to prelease, about six months of demand. Power, equipment, and approvals will decide which projects start on time.

Expect more projects to be phased, paired with on-site power, and placed wherever power is available. Policy is shifting as well: the Texas governor plans to ask the 2027 legislature to end state data center incentives.

How to find data center projects with project data

Here is how to turn the signals above into a list your team can work.

Search by project type and territory

Choose Data Centers as the project type and set your territory. If data centers are your focus everywhere, the Vertical Market plan covers one project type across all of the U.S. and Canada.

Filter by stage

Focus on planning and design. That is when owners pick builders, builders set their partner lists, and engineers write the specifications.

Check the value and materials list

Each Construct-A-Lead record includes an estimated value and a materials list, so you can confirm a project needs what you sell before you call.

Call the named contact

Every project includes at least one named contact with a phone number and email, and you can read how we verify every project. Ask who else is on the team: the builder, the engineers, and the owner’s representative.

Set alerts and rank your leads

Turn on email alerts so new data center projects reach you as they are published. Then rank them with a lead scoring checklist, and use our guide to finding construction leads for every other channel.

Want to see what is planned in your market? Start your free test drive: 3 days or 5 projects, whichever comes first, with no credit card required.

Frequently asked questions

Is data center construction slowing down?

Not overall. U.S. data center construction spending hit a record $96.5 billion annual rate in September 2026, up 90% in a year, and AIA forecasts another 24.7% rise in 2027. Some projects are slowing, though: grid connections can take more than four years, some transformers more than three years, and moratoriums and electrician shortages are delaying others.

How long does it take to build a data center?

It depends on size and power. A first building or data hall can be ready in about a year: Bell Canada began building near Regina in April 2026 and expects its first data hall in the first half of 2027. Large campuses are built in phases over many years, and waiting for a grid connection can add years before construction starts.

How much does it cost to build a data center per MW?

Cushman & Wakefield’s 2026 guide puts the all-in cost of a new data center in the U.S. and Canada at about $17.6 million per MW, excluding computer chips, up 21% since late 2024. Turner & Townsend puts U.S. construction cost alone at about $12.08 per watt. Power infrastructure is the largest single cost category.

How much data center capacity is under construction in the U.S.?

It depends on what is counted. CBRE reports 7,481 MW under construction in eight primary North American markets in the first half of 2026, 80% of it preleased. JLL, which also counts self-built campuses and newer markets, puts North American capacity under construction at 66 GW. Both say demand is outrunning supply.

What trades work on data center construction?

Electrical and mechanical contractors have some of the largest scopes: mechanical, electrical, and plumbing work runs 30% to 50% of a hyperscale project’s cost, according to Linesight. Concrete, structural steel, fire protection, low-voltage and security, and site contractors also have large scopes. Electricians are in short supply, so qualified electrical crews are especially sought after.

How can I find data center construction projects near me?

Watch local rezoning cases, utility agreements, and tax incentive votes, or use a project database you can filter by project type and location. Construct-A-Lead covers commercial construction across all of the U.S. and Canada, with data centers as a project type, and every project is confirmed by phone. A free test drive (3 days or 5 projects, no credit card) shows what is planned near you.

Sources

  1. U.S. Census Bureau, Value of Private Construction Put in Place, seasonally adjusted (released November 2, 2026; September 2026 figures preliminary)
  2. U.S. Census Bureau, Value of Private Construction Put in Place, not seasonally adjusted (released November 2, 2026)
  3. AGC, construction spending release for September 2026 (November 2, 2026)
  4. AIA, July 2026 Consensus Construction Forecast (July 20, 2026)
  5. CBRE, North America Data Center Trends H1 2026 (August 27, 2026)
  6. JLL, North America Data Center Report, midyear 2026 (August 11, 2026)
  7. JLL, 2026 Global Data Center Outlook (January 5, 2026)
  8. ERCOT, presentation to the Texas Senate on large loads (July 29, 2026)
  9. Reuters, U.S. power companies scramble to secure equipment (Wood Mackenzie data) (July 9, 2026)
  10. Linesight, MEP subcontractor procurement for hyperscale data centre construction (April 28, 2026)
  11. AGC and NCCER, 2026 Workforce Survey, data center results (September 3, 2026)
  12. AGC Data DIGest, producer prices for August 2026 (September 11, 2026)
  13. Cushman & Wakefield, 2026 Data Center Development Cost Guide (release) (September 3, 2026)
  14. Turner & Townsend, Data Centre Construction Cost Index 2026-27 (October 22, 2026)
  15. Office of the Texas Governor, directive to halt data center permits (September 21, 2026)
  16. Federation of American Scientists, Before Breaking Ground (September 10, 2026)
  17. Government of Alberta, data centres and the grid (accessed November 13, 2026)
  18. Government of Alberta, data centres in Alberta (accessed November 13, 2026)
  19. CP24, Ontario data centre plan (August 13, 2026)
  20. WWNO, Meta expands Richland Parish data center project (July 14, 2026)
  21. Meta, new data center in Lebanon, Indiana (February 11, 2026)
  22. Louisiana Economic Development, Amazon northwest Louisiana investment (August 18, 2026)
  23. Mississippi Public Broadcasting, Amazon central Mississippi investment (April 9, 2026)
  24. Epoch AI, Stargate New Mexico (Project Jupiter) (updated July 31, 2026)
  25. Simpson Thacher, financing for the Saline Township data center project (April 27, 2026)
  26. The Energy Mag, Microsoft Fairwater (April 20, 2026)
  27. WTOC, OpenAI data center in Effingham County (July 22, 2026)
  28. CP24, Bell Canada Saskatchewan AI data centre milestone (October 1, 2026)